15 April 2026                                Business Spotlight  |  Editorial Extra  |  News  |  Podcasts  |  About us  |  Home

Industry Guide


Archive




1997-07-14 LRT-001

London Regional Transport

Bakerloo Line back in business


keywords: click to search

Bakerloo line
London Regional Transport
London Transport
London Underground
Operation Hard Hat




Words in [single square brackets] included hyperlinks in the original document

Words in [[double square brackets]] are editorial additions or corrections

Words in [[[triple square brackets]]] indicate embedded images or graphics in the original document. (These are not usually archived unless they contain significant additional information.)




< operators’ contracts index





Press release


London Regional Transport

Bakerloo Line back in business


  date 14 July 1997
  source London Regional Transport
  type Press release

A full service resumed on the Bakerloo Line today, 14 July 1997, after a seven month closure between Piccadilly Circus and Elephant & Castle. The re-opening, which marks the end of Operation Hard Hat, follows work necessary to strengthen the ninety-year-old running tunnels beneath the River Thames between Embankment and Waterloo

The £30 million project was completed on time and within budget. During the closure an estimated 82,000 customers a day had to find alternative means of travelling in central London. In spite of the provision of a fast and frequent alternative bus service between Oxford Circus and Waterloo, the bulk of displaced customers used the heavily congested Northern Line.

Travelling in the cab of the first train in public service to pass through the strengthened tunnels (0528 from Elephant & Castle) were MPs Kate Hoey (Lab Vauxhall) and Simon Hughes (Lib Dem Southwark and Bermondsey).

Peter McMahon, the Bakerloo Line's General Manager, commented: "It is so encouraging to receive such generous support from two of London's most popular Members of Parliament whose constituencies are served by the Bakerloo Line. Although the Underground's funding problems are well known, there is good news about and this certainly fits the bill. The Bakerloo Line is now fit for another hundred years and will continue to provide a reliable and comfortable link for commuters and shoppers alike travelling between the North and South Bank."

The seven month closure was seized upon as an opportunity to carry out other infrastructure improvements to minimise further disruption to passengers. The most noticeable result is the smoother ride achieved by installing a higher grade of track.